BP Solar Photovoltaic Panels
Multiple Locations, United States
Lendlease acted as the program manager, working with contractors across the United States to install Photovoltaic panels and modules at multiple facilities.
BP Solar Photovoltaic Panels
- Client
- BP Solar United States, Inc.
- Location
- Multiple Locations, United States
- Completion
- 2008
- Assignments
- Program Management
- Architect
- Various
Project outcome
A typical photovoltaic project involves a system that has 265 kilowatts to one megawatt of power output. Based on each facility's energy needs and roof type, a unique photovoltaic module support system was engineered accordingly.
Projects:
- Wal-Mart - Palm Springs
- Wal-Mart - Beaumont
- Sam's Club - La Habra and Glendora
- FedEx Freight - Whittier and Fontana
- Palo Verde Community College - Blythe
- Colorado State University - Pueblo, Colorado
Photovoltaic systems can supply between 10-40 percent of a conventional facility's electrical needs, integrated with existing electrical and mechanical systems. Each of the BP Solar projects was completed in a three to six month timeframe. The overall program spanned for 18 months and involved a total of eight projects at the various locations.